- Chair Jim Miller announced the "quiet phase" of fund raising has been completed with 25 donors pledging $250,000. Add the $50,000 the City received from KCMO, the EAGC has reached the 50% mark on the necessary funding for completion of the project.
- There was discussion of "tweaking" the plans to reflect a completion target of $400,000/ $450,000, the extra $150,000 needed was "not very difficult" to raise according to Mayor Jerry Bos.
- There was a Fund Raising Subcommittee meeting this past Saturday.
- Discussion vacillated between the $600,000 target vs $450,000 for fund raising. It was pointed out by Kristopher Dabner of the Greensman, that without construction plans it is very difficult to get a more exact idea of costs that would be determined by RFPs.
- Glenda Negrelli pointed out clubs like the Women's Club may want to contribute, she added "we have quite a bit of money".
- Chairman Miller said some of those who made pledges would like to see a larger contribution on the part of the City.
- Lynn Hinkle would like a statement of strong support from the BOA and Mayor to be used to stimulate donations based on commitment of the City. "We need to push it to the next level".
- Jerry was asked on best guess when Barry Road would be completed, he replied late 2011 or early 2012.
- The term monuments is out, entrances is in.
- The EAGC passed a motion/recommendation to the BOA (to be presented Tuesday night) recommending expenditure of up to $8,000 for construction plans and the active solicitation of the checks for the first round of pledges.
Tuesday, January 5, 2010
Making An Entrance
Unofficial Official Minutes of the Entrance Advisory Group Committee (EAGC)