Scope of Work:

Platte County is working with the City of Kansas City Missouri to design and construct Barry Road from Potomac to Chariton based on an ultimate three lane road with bike lanes but only build a 28 foot wide portion of the roadway with two 14 foot lanes. This improvement will still provide 2 travel lanes, curbs, storm sewers, sidewalks, streetlights and vertical safety improvements. These improvements should work with the existing budget.

In the future when traffic demands increase and funds are identified for construction the remaining portion of the three lane roadway may be completed by the city of Kansas City.

Design:

SKW (Shafer, Kline, and Warren) has requested, prior to issuance of final drawings that PCPW verify all Right of Way and Easements are acceptable to the property owners. If any changes are necessary, they will make amendments and then issue the final drawings. PCPW has agreed to this request.

Property Acquisition:

PAR Electrical (Acting R/W Agent for PCPW) has contacted all of the property owners with regards to R/W and easement acquisition. Twelve out of the thirty property owners have signed the Temporary Easement and/or Right-of-Way Deeds that affect their property. PCPW is currently negotiating with the balance of the owners and lien holders to obtain their signatures. Condemnation procedures have been implemented as required.



Utility Relocation:

All utilities along the road that will conflict with the improvement will need to be relocated. Platte County is coordinating with the utilities to address any conflicts. The utility relocation schedule is contingent upon the individual utility companies schedule and coordination of relocation activities in the Barry Road improvement phases occurring to the east of this project. All relocations not done prior to the start of this project will begin Summer 2009 in coordination with construction.

Platte County will continue holding coordination meetings with all the utility companies, Kansas City and the design engineer (SKW).

Phone, electric, and cable TV utilities are currently working to relocate their lines prior
to construction beginning.


Bidding:

Platte County’s goal is to bid the project in early 2009, pending successful design, property acquisition and utility relocations.

Construction:

Construction will occur after property acquisition, utility relocation and bidding is complete. Currently anticipate starting Phase I Construction Summer 2009.